More updates from Ponto!
7304:
Roof, completed.
Mechanical ductwork, completed.
Plumbing, completed.
Stairs and basement slab, completed.
Windows and Doors, nearly completed.
Sewer and Water services, nearly completed.
Electrical, 50% completed.
Final grading site, working.
7305:
Framing nearly complete.
Roofing, completed.
Windows and Doors, nearly completed.
Sewer and Water, nearly completed.
Mechanicals, completed.
Plumbing, started Friday.
Electrical, starting soon.
Final grading site, TBD.