More updates from Ponto!

7304:

  • Roof, completed.

  • Mechanical ductwork, completed.

  • Plumbing, completed. 

  • Stairs and basement slab, completed. 

  • Windows and Doors, nearly completed. 

  • Sewer and Water services, nearly completed.

  • Electrical, 50% completed. 

  • Final grading site, working.

7305:

  • Framing nearly complete. 

  • Roofing, completed. 

  • Windows and Doors, nearly completed. 

  • Sewer and Water, nearly completed. 

  • Mechanicals, completed. 

  • Plumbing, started Friday. 

  • Electrical, starting soon. 

  • Final grading site, TBD.